Monica develops a monitoring and evaluation plan for tracking progress during the procurement of construction services for the construction project she is managing. Which portion of the procurement strategy is Monica focused on during this time? A: Procurement phases B: Contract payment types C: Delivery methods D: Bid documents

PMP Certification 2021 practice questions.
Source: https://thorteaches.com/ Free PMP practice exam questions for the 2021 PMP exam version.

ANSWER

The right answer is A.

The procurement strategy can also include information on procurement phases. Information may include:

-sequencing or phasing of the procurement, a description of each phase and the specific objectives of each phase;
-procurement performance indicators and milestones to be used in monitoring;
-criteria for moving from phase to phase;
-monitoring and evaluation plan for tracking progress; and
-process for knowledge transfer for use in subsequent phases.