While his project is executing on their well-developed project management plan, Marco reviews all of the process groups under Executing. He realizes he needs to focus a little bit more on Project Resource Management. Which of the following items is Marco NOT going to focus on? A: Manage Stakeholder Engagement B: Develop Team C: Acquire Resources D: Manage Team

PMP Certification 2021 practice questions.
Source: https://thorteaches.com/ Free PMP practice exam questions for the 2021 PMP exam version.

ANSWER

The right answer is A.

Managing Stakeholder Engagement is part of the Project Stakeholder Management process. Since Marco is focusing solely on Project Resource Management, he’ll be looking at acquiring resources, developing the team and managing the team.