Peta's been asked to develop a project schedule that will give the Project Management Office an idea of the complexity and interdependencies of the tasks required to move their Imaging Department from the basement of their main hospital to a nearby building they're thinking of purchasing. There are no dates and right now, they are unconcerned about how long each task would take. What type of project schedule is Peta going to develop? A: Milestone chart B: Project schedule network diagram C: Bar chart D: Work Breakdown Structure

PMP Certification 2021 practice questions.
Source: https://thorteaches.com/ Free PMP practice exam questions for the 2021 PMP exam version.

ANSWER

The right answer is B.

Peta is developing a project schedule network diagram. These diagrams are commonly presented in the activity-on-node diagram format showing activities and relationships without a time scale, sometimes referred to as a pure logic diagram.