The expectations of the project manager as noted in the Key Concepts for Integration Management sections in the PMBOK® Guide do not change in an adaptive environment, but control of the detailed product planning and delivery is delegated to the ______.
A: team
B: product owner
C: scrum master
D: program manager
Knowledge Area:
Agile Practice Guide
Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
A:
The project manager’s focus is on building a collaborative decision-making environment and ensuring the team has the ability to respond to changes.