Baselines are often an artifact of attempted prediction. In agile, the team
limits its estimation to how far out in advance from present time?

A: Until the project is completed
B: The next few months
C: The next few weeks
D: The next few days

Knowledge Area:
Agile Practice Guide

Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
C:
Baselines are often an artifact of attempted prediction. In agile, the team
limits its estimation to the next few weeks at most. In agile, if there is low
variability in the team’s work and if the team members are not multitasking,
the team’s capacity can become stable. This allows better prediction for the
next couple of weeks.