Baselines are often an artifact of attempted prediction. In agile, the team
limits its estimation to how far out in advance from present time?

A: Until the project is completed
B: The next few months
C: The next few weeks
D: The next few days

Knowledge Area:
Agile Practice Guide

Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
C:
Baselines are often an artifact of attempted prediction. In agile, the team
limits its estimation to the next few weeks at most. In agile, if there is low
variability in the team’s work and if the team members are not multitasking,
the team’s capacity can become stable. This allows better prediction for the
next couple of weeks.

[/show_more]

LIVE!!

Our Upgraded CISSP Flashcards are OUT!

15% off Launch SALE!

  • 2,800+ Flashcards from all 8 CISSP domains
  • Study from anywhere on any device at any time (web, Android, iOS)
  • Learn more in less time with optimized spaced repetitions
  • Focus on your weak areas first with the confidence-based algorithm
  • Do short 10-term sessions or longer ones as they match your schedule
  • Strengthen your long‑term memory using active recall with immediate answer reveal and self‑rating
  • Track your progress instantly - Mastery %, Confidence Gained, and Cards Studied update after each round
  • Keep motivation high - Instant feedback, progress meters, variable rewards, and social leaderboards
  • Stay on schedule with automated study reminders
Brainscape_s CISSP mobile dashboard