What is the general guideline for how long a team should go before demonstrating whatever they have as a working product to the decisionmakers?

A: One week
B: Three weeks
C: One month
D: Two weeks

Knowledge Area:
Agile Practice Guide

Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
D:
As a general guideline, demonstrate whatever the team has as a working product at least once every 2 weeks. That frequency is enough for most teams, so team members can get feedback that prevents them from heading in a wrong direction. That is also frequent enough so that the teams can keep the product development clean enough to build a complete product as often as they want or need to.

[/show_more]

LIVE!!

Our Upgraded CISSP Flashcards are OUT!

15% off Launch SALE!

  • 2,800+ Flashcards from all 8 CISSP domains
  • Study from anywhere on any device at any time (web, Android, iOS)
  • Learn more in less time with optimized spaced repetitions
  • Focus on your weak areas first with the confidence-based algorithm
  • Do short 10-term sessions or longer ones as they match your schedule
  • Strengthen your long‑term memory using active recall with immediate answer reveal and self‑rating
  • Track your progress instantly - Mastery %, Confidence Gained, and Cards Studied update after each round
  • Keep motivation high - Instant feedback, progress meters, variable rewards, and social leaderboards
  • Stay on schedule with automated study reminders
Brainscape_s CISSP mobile dashboard