What is the general guideline for how long a team should go before demonstrating whatever they have as a working product to the decisionmakers?
A: One week
B: Three weeks
C: One month
D: Two weeks
Knowledge Area:
Agile Practice Guide
Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
D:
As a general guideline, demonstrate whatever the team has as a working product at least once every 2 weeks. That frequency is enough for most teams, so team members can get feedback that prevents them from heading in a wrong direction. That is also frequent enough so that the teams can keep the product development clean enough to build a complete product as often as they want or need to.
[/show_more]