Which of the following is NOT contained within the Procurement Strategy?

A: Procurement delivery methods
B: Type of agreements
C: Procurement phases
D: Procurement assumptions and
constraints

Knowledge Area:
Plan Procurement Management

Source: ThorTeaches.com PMP practice tests

Answer


D:
Procurement assumptions and constraints is only contained within the Procurement Management Plan. The Procurement Strategy contains the procurement delivery methods, type of agreements and procurement phases.