Logan is managing a project for his small chain of bakeries to begin selling homemade donuts in addition to the pastries, pies and cookies they already offer. He identities that not only do they only have a certain amount of money they can spend before eating into their operating budget, but also that only one other employee is available to help him procure the equipment he’ll need to make the donuts. What is Logan analyzing as he looks at defining the scope of his project?

A: Assumptions
B: Constraints
C: Major deliverables
D: Assumptions

Knowledge Area:
Define Scope

Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
B:
The preparation of a detailed project scope statement builds upon the major deliverables, assumptions, and constraints that are documented during project initiation. And contraints are defined as any restriction that defines a project’s limitations. Logan’s discovered both a financial constraint and a human resource constraint that he has to work with in order to proceed with his project.

[/show_more]

LIVE!!

Our Upgraded CISSP Flashcards are OUT!

15% off Launch SALE!

  • 2,800+ Flashcards from all 8 CISSP domains
  • Study from anywhere on any device at any time (web, Android, iOS)
  • Learn more in less time with optimized spaced repetitions
  • Focus on your weak areas first with the confidence-based algorithm
  • Do short 10-term sessions or longer ones as they match your schedule
  • Strengthen your long‑term memory using active recall with immediate answer reveal and self‑rating
  • Track your progress instantly - Mastery %, Confidence Gained, and Cards Studied update after each round
  • Keep motivation high - Instant feedback, progress meters, variable rewards, and social leaderboards
  • Stay on schedule with automated study reminders
Brainscape_s CISSP mobile dashboard