A Lessons Learned Register is one output of which project management process group?
A: Develop Project Charter
B: Manage Project Knowledge
C: Perform Integrated Change Control
D: Control Scope
Knowledge Area:
Manage Project Knowledge
Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
B:
A Lessons Learned Register is one of the outputs of the Manage Project Knowledge process group.