Victoria decides that the only way her team is going to get the Standard Operating Procedures completed on time for the new candies her company’s preparing to manufacture, is if all ten team members drop everything and work on the SOPs exclusively for the next six business days. This is an example of what agile team technique?
A: Swarming
B: Pairing
C: Panicking
D: Mobbing
Knowledge Area:
Agile Project Management
Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
D:
Mobbing is correct. This is a technique in which multiple team members focus simultaneously and coordinate their contributions on a particular work item.