While his project is executing on their well-developed project management plan, Marco reviews all of the process groups under Executing. He realizes he needs to focus a little bit more on Project Resource Management. Which of the following items is Marco NOT going to focus on?

A: Manage Stakeholder Engagement
B: Develop Team
C: Acquire Resources
D: Manage Team

Knowledge Area:
Executing

Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
A:
Managing Stakeholder Engagement is part of the Project Stakeholder Management process. Since Marco is focusing solely on Project Resource Management, he’ll be looking at acquiring resources, developing the team and managing the team.

[/show_more]