While his project is executing on their well-developed project management plan, Marco reviews all of the process groups under Executing. He realizes he needs to focus a little bit more on Project Resource Management. Which of the following items is Marco NOT going to focus on?

A: Manage Stakeholder Engagement
B: Develop Team
C: Acquire Resources
D: Manage Team

Knowledge Area:
Executing

Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
A:
Managing Stakeholder Engagement is part of the Project Stakeholder Management process. Since Marco is focusing solely on Project Resource Management, he’ll be looking at acquiring resources, developing the team and managing the team.

[/show_more]

LIVE!!

Our Upgraded CISSP Flashcards are OUT!

15% off Launch SALE!

  • 2,800+ Flashcards from all 8 CISSP domains
  • Study from anywhere on any device at any time (web, Android, iOS)
  • Learn more in less time with optimized spaced repetitions
  • Focus on your weak areas first with the confidence-based algorithm
  • Do short 10-term sessions or longer ones as they match your schedule
  • Strengthen your long‑term memory using active recall with immediate answer reveal and self‑rating
  • Track your progress instantly - Mastery %, Confidence Gained, and Cards Studied update after each round
  • Keep motivation high - Instant feedback, progress meters, variable rewards, and social leaderboards
  • Stay on schedule with automated study reminders
Brainscape_s CISSP mobile dashboard