Peta’s been asked to develop a project schedule that will give the Project Management Office an idea of the complexity and interdependencies of the tasks required to move their Imaging Department from the basement of their main hospital to a nearby building they’re thinking of purchasing. There are no dates and right now, they’re unconcerned about how long each task would take. What type of project schedule is Peta going to develop?
A: Milestone chart
B: Project schedule network diagram
C: Bar chart
D: Work Breakdown Structure
Knowledge Area:
Develop Schedule
Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
B:
Peta is developing a project schedule network diagram. These diagrams are commonly presented in the activity-on-node diagram format showing activities and relationships without a time scale, sometimes referred to as a pure logic diagram.
[/show_more]