Peta’s been asked to develop a project schedule that will give the Project Management Office an idea of the complexity and interdependencies of the tasks required to move their Imaging Department from the basement of their main hospital to a nearby building they’re thinking of purchasing. There are no dates and right now, they’re unconcerned about how long each task would take. What type of project schedule is Peta going to develop?

A: Milestone chart
B: Project schedule network diagram
C: Bar chart
D: Work Breakdown Structure

Knowledge Area:
Develop Schedule

Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
B:
Peta is developing a project schedule network diagram. These diagrams are commonly presented in the activity-on-node diagram format showing activities and relationships without a time scale, sometimes referred to as a pure logic diagram.

[/show_more]

LIVE!!

Our Upgraded CISSP Flashcards are OUT!

15% off Launch SALE!

  • 2,800+ Flashcards from all 8 CISSP domains
  • Study from anywhere on any device at any time (web, Android, iOS)
  • Learn more in less time with optimized spaced repetitions
  • Focus on your weak areas first with the confidence-based algorithm
  • Do short 10-term sessions or longer ones as they match your schedule
  • Strengthen your long‑term memory using active recall with immediate answer reveal and self‑rating
  • Track your progress instantly - Mastery %, Confidence Gained, and Cards Studied update after each round
  • Keep motivation high - Instant feedback, progress meters, variable rewards, and social leaderboards
  • Stay on schedule with automated study reminders
Brainscape_s CISSP mobile dashboard