When a Vice President begins complaining to Project Manager Anastasia that she doesn’t feel she’s being given enough information to keep her as informed as she needs to be, what project document produced as part of the Identify Stakeholders process group should Anastasia look at to remind herself of this VP’s assessment information?

A: Project Management Plan
B: Assumption Log
C: Risk Register
D: Stakeholder Register

Knowledge Area:
Identify Stakeholders

Source: ThorTeaches.com PMP practice tests

Answer


D:
The main output of the Identify Stakeholders process is the stakeholder register. This document contains information about identified stakeholders that includes but is not limited to:
-Identification information
-Assessment information
-Stakeholder classification

show less