When a Vice President begins complaining to Project Manager Anastasia that she doesn’t feel she’s being given enough information to keep her as informed as she needs to be, what project document produced as part of the Identify Stakeholders process group should Anastasia look at to remind herself of this VP’s assessment information?

A: Project Management Plan
B: Assumption Log
C: Risk Register
D: Stakeholder Register

Knowledge Area:
Identify Stakeholders

Source: ThorTeaches.com PMP practice tests
[show_more more=Answer]
D:
The main output of the Identify Stakeholders process is the stakeholder register. This document contains information about identified stakeholders that includes but is not limited to:
-Identification information
-Assessment information
-Stakeholder classification

[/show_more]

LIVE!!

Our Upgraded CISSP Flashcards are OUT!

15% off Launch SALE!

  • 2,800+ Flashcards from all 8 CISSP domains
  • Study from anywhere on any device at any time (web, Android, iOS)
  • Learn more in less time with optimized spaced repetitions
  • Focus on your weak areas first with the confidence-based algorithm
  • Do short 10-term sessions or longer ones as they match your schedule
  • Strengthen your long‑term memory using active recall with immediate answer reveal and self‑rating
  • Track your progress instantly - Mastery %, Confidence Gained, and Cards Studied update after each round
  • Keep motivation high - Instant feedback, progress meters, variable rewards, and social leaderboards
  • Stay on schedule with automated study reminders
Brainscape_s CISSP mobile dashboard